Updates on the ADU that is being built using the Conventional Construction Process.
In the background photos you see the excavation has been shored with Metal I Beams and Steel Plates for safety against cave-in of soil.
The I Beams are set to a plumb line and set in concrete. The holes are 24″ in diameter x 11 feet deep into hard rock. This creates (3) sides of Structural Foundation Wall. Rebar will be installed through the beams as per plan. The Foundation wall will be Concrete “Shotcrete” and screeded smooth.
New Updates – 6/1/2022
Updates on the ADU that is being built using the Conventional Construction Process.
In the background photos you see the excavation has been shored with Metal I Beams and Steel Plates for safety against cave-in of soil.
The I Beams are set to a plumb line and set in concrete.
The holes are 24″ in diameter x 11 feet deep into hard rock.
This creates (3) sides of Structural Foundation Wall.
Rebar will be installed through the beams as per plan.
The Foundation wall will be Concrete “Shotcrete” and screeded smooth.
More updates as job progress.